How much is the decoration of three rooms and two

2022-07-22
  • Detail

Project 1: Foundation Engineering

shovel the wall (gypsum ash) 1140.00

remove the wall and floor tiles 3000.00

wall blank base treatment 660.00

wall/ground cement mortar leveling 1400.00

seal the door head 120.00

door pocket base (Blockboard) 700.00

remove the brick wall (120 mm) 175.00

remove the original doors and windows and sets 220.00

light brick wall (120 ±mm double-sided plastering) 2100.00

hole after wall removal Paint 360.00

cabinet back sealing cement board 440.00

item 2: Waterway Circuit engineering

strong and weak current construction (lump sum price) 6300.00

waterway construction (lump sum price) 2200.00

balcony water outlet 600.00

Project III: guest restaurant and aisle

emulsion paint base treatment (putty) 4600.00

emulsion paint 1840.00

gypsum board straight light trough ceiling 1848.00

gypsum board shaped ceiling 1035.00

TV background wall 800.00

shoe cabinet (including door and ecological board) 2480.00

item 4: master bedroom

emulsion paint base treatment (putty) 960.00

emulsion paint 384.00

wardrobe cabinet body (ecological board) 2640.00

wardrobe door (ecological board) 247.50

item 5: secondary bedroom

emulsion paint base treatment (putty) 860.00

emulsion paint 344.00

wardrobe cabinet body (ecological board)2400.00

wardrobe door (ecological board) 247.50

item 6: study

emulsion paint base treatment (putty) 600.00

emulsion paint 240.00

wardrobe body (ecological board) 2160.00

wardrobe door (ecological board) 330.00

item 7: Kitchen

General specification of wall tiles (300 × 450 < size ≤ 300 × 600) 1210.00

common specification of floor tiles (size 300 × 300) 275.00

waterproof treatment of kitchen 315.00

kitchen and sanitary package pipes 520.00

paving of doorway stone 50.00

item 8: bathroom

general specification of wall tiles (300 × 450 < size ≤ 300 × 600) 1430.00

common specification of floor tiles (size 300 × 300) 385.00

toilet backfilling and surface leveling 490.00

toilet waterproof treatment 900.00

kitchen and sanitary package pipes 650.00

door stone paving 50.00

toilet sewer protection works 400.00

Item 9: balcony

emulsion paint base treatment (batch scraping greasy) 140.00

emulsion paint 56.00

General specification of floor tiles (200 × 200 < size ≤ 800 × 800) 385.00

common specification of wall tiles (300 × 450 < size ≤ 300 × 600) 880.00

balcony railing base tiling 210.00

storage cabinet (ecological board) 1920.00

storage cabinet door (ecological board) 660.00

balcony waterproof treatment 315.00

item 10: miscellaneous

materials upstairs cost 300.00

materials transportation cost 300.00

indoor garbage removal cost 300.00

lamp installation 200.00

sanitary ware installation 150.00

hardware installation 100.00

finished product protection 300.00

super high operation cost 600.00

ground fixation 300.00

item 11: other charges

third party supervision 1599.00

the above is 120 square meters in Wuhan The detailed quotation for the half package decoration of three bedrooms and two living rooms. For the same area, the decoration quotation will vary due to different decoration companies and house types, so you can use the above quotation as a reference. If you want to know the quotation for the decoration of your house, the Wuhan home decoration network decoration bidding platform can select 3 to 4 suitable decoration companies to measure the house for free and formulate the decoration plan, which you can compare, There are also some decoration deductions waiting for you. For details, please visit the activity page http://whjzw.net/zb/。